JH Kelly was selected by Grays Harbor Energy to act as primary general contractor to complete this 500MW natural gas combined cycle 2x 1 power plant in Satsop, Washington. The plant was originally started in 2001 but halted at an estimated 50% completion (primarily the civil/structural work only). The project resumed with new ownership. Included in the JH Kelly work scope was the assembly/erection of a General Electric D-11 steam turbine set; the final assembly and alignment of two General Electric combustion turbine generator sets; completion of two Aalborg heat recovery boilers; BOP equipment installation/alignment; 72, 544 lf of piping; structural steel completion; civil scope completion; BOP electrical, controls and heat tracing; BOP paint and insulation; and the switchyard/substation.

  • Two GE PG7241FA combustion turbine generator sets
  • 500 MW Power Plant
  • 72,544 Lineal Feet of Pipe
  • 600 Cubic Yards of Concrete
  • 350 Tons of Structural Steel

Grays Harbor Energy Center | 500 MW Natural Gas Power Plant

Grays Harbor Energy Center | 500 MW Natural Gas Power Plant

Client
Grays Harbor Energy
Location
Satsop, WA
JH Kelly Role
Industrial General Contractor
Market Sector
Power Generation
Year Completed
2008