Projects

SPECIAL FEATURES: 65MW steam turbine generator and 35,000 lineal feet of pipe

Projects

Simpson Tacoma Cogeneration Project

TACOMA, WA

Simpson Tacoma Kraft contracted JH Kelly to be the lead during the construction of its new Cogeneration Project.

The project involved the installation of a new steam turbine generation set, exhaust steam condenser, cooling towers, power distribution switchyard, associated equipment and all steam, feedwater, cooling water and other related piping systems.

A new turbine hall was constructed on a site that was previously occupied by an old power house.

JH Kelly performed miscellaneous engineering assistance, constructability reviews, and provided value engineering options to decrease costs, minimize paper machine down times and improve existing piping and mechanical systems.