PSM – Calpine Delta, Pittsburgh, CA

Working closely with leading aftermarket service provider for Gas Turbine Power Plants worldwide, Power Systems Mfg (PSM) has made JH Kelly their go-to union contractor to service combined-cycle power plants across the United States.

After JH Kelly’s performance during the capital construction of PGE’s Port Westward power plant under PSM, we garnered their trust and became a traveling contractor for PSM.

This relationship brought us to Calpine Delta power plant, in Pittsburgh, California.

  • Outage lasted 35 days
  • (2) Siemens Westinghouse turbines
  • $1,000,000
  • Turbine rebuild major outage
  • Showed¬†JHK’s ability to perform turbine re-builds on the road, out of town