Projects

SPECIAL FEATURES: 12,000 feet of 16" underground chilled water pipe, and a nine month duration

Projects

NAU Chilled Water Project

Flagstaff, AZ

JH Kelly installed 12,000 feet of 16″ underground chilled water pipe and constructed a new chiller plant on a new concrete floor in the old bus barn building as prime contractor on this project. Much of the underground pipe ditch had to be excavated out of solid rock. Additionally, structural steel was installed through the roof to accommodate the new cooling towers.

Minimizing campus disruption was paramount to our client. We routed piping in tunnels in high traffic areas and maintained safe student access in other areas.

Printable Page

821 Third Avenue / PO Box 2038 / Longview, WA 98632T 360.423.5510 / F 360.423.9170 / mail@jhkelly.com