Chelan County PUD – North Shore Chelan Substation
JH Kelly was hired as general contractor to demolish existing foundations and structure on the property, and JHK installed all new transformer foundations, and transformer concrete containment pits. The scope also included conduit, trenching and grounding for all structures. Limited commercial wiring was also completed for Chelan County PUD.
Project costs were $300,000 and was completed in 6 weeks. There were no change orders or safety incidents on this project.