Project ProfileSouthwest Washington Medical Center Vancouver, WA 
JH Kelly was awarded the full mechanical buildout on the Southwest Washington Medical Center tenant improvement of floors 4, 5 and 6 including adding additional water heater capacity to the 8-story tower. JH Kelly was contracted to perform the work on a GMP basis with all savings back to the owner. The project consisted of adding 80 patient rooms with JH Kelly self-performing all the plumbing and wetside HVAC piping. Subcontracted work included sheetmetal, controls, fire caulking, insulation, test and balance and medical gas certification. The project was completed in June 2009. Special points of interest: - Tenant build-out of floors 4, 5, and 6
- 80 new patient rooms
- Peak manpower: 35
- 12-month duration