PROJECTS JH Kelly logo
 
Previous Profile Next Profile

Project Profile

BP Sour Water Handling Upgrade Project
Blaine, WA

Installation Site for Conoco SRU Facility

The project will increase the refinery’s sour water handling capacity by over 25%. This will be accomplished by installing a new flash drum, re-traying a non-phenolic stripper column, and installing new heat exchangers, pumps, and an H2S absorber.

Within the construction phase, JH Kelly’s portion of the field work will be executed over a one-year period. The current construction schedule sets mechanical completion for mid-October 2010.

As the general mechanical contractor for the project, JH Kelly has been assigned as the lead for all trade contractors: providing constructability input through the detailed engineering phase; coordinating the field work of the other trade contractors; and developing and maintaining the overall project schedule.

Construction phase highlights:
1. No recordable injuries.
2. Planned, scheduled and executed a two-week, double-shift unit outage to re-tray a stripper column, and install new piping and exchangers. All work was successfully completed ahead of schedule.
3. Set a 110,000 pound, 14’ diameter x 45’ long drum within a new steel structure, coordinating and working directly with both the heavy lift and heavy haul contractors.

General Construction Quantites:
  • Excavation—2,900 CY
  • Concrete—550 CY
  • Steel—150 TN
  • Equipment Install—1 flash drum; 1 H2S absorber; 3 exchangers; 1 air cooler; 6 pumps; 1 oxygen tank
  • Pipe (Install)—7,500 LF
  • Pipe (Field Fab.)—900 LF
  • Pipe (Demo)—1,500 LF
  • Instrument (Install)—100 EA
 
  
To print pdf version
 

JH Kelly is a 4th generation family-owned construction company serving the greater Pacific Northwest. We function as a self-performing industrial general contractor at process facilities. Our reputation for completing difficult process piping jobs is well known throughout the region and our success has led us to offer 3rd party services as a piping fabricator or module fabricator. Our integrated project approach includes self-performing concrete placement, functioning as a steel erector and providing equipment setting, millwrighting, and electrical services. For commercial HVAC projects, we can be found under tower cranes providing trade services as a plumbing contractor or mechanical contractor on a subcontracted basis.